Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | ACPR-1000 |
Owner | Jiangsu Nuclear Power Corporation |
Operator | Jiangsu Nuclear Power Corporation |
Timeline
Construction Start | Wednesday, 7 September 2016 |
---|---|
First Criticality | Tuesday, 4 May 2021 |
First Grid Connection | Tuesday, 11 May 2021 |
Commercial Operation | Wednesday, 2 June 2021 |
Specifications
Capacity Net | 1060 MWe |
---|---|
Capacity Gross | 1118 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1000 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2021 | 1060 | 5636 | 5786.59 | 100.00 | 98.90 | 98.90 | 96.50 | 96.50 |
2022 | 1060 | 7643 | 7538.05 | 87.20 | 86.80 | 91.30 | 81.20 | 86.80 |