Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | EPR-1750 |
Owner | Guangdong Taishan Nuclear Power Joint Venture Co Ltd |
Operator | Guangdong Taishan Nuclear Power Joint Venture Co Ltd |
Timeline
Construction Start | Thursday, 15 April 2010 |
---|---|
First Criticality | Tuesday, 28 May 2019 |
First Grid Connection | Sunday, 23 June 2019 |
Commercial Operation | Saturday, 7 September 2019 |
Specifications
Capacity Net | 1660 MWe |
---|---|
Capacity Gross | 1750 MWe |
Thermal Capacity | 4590 MWt |
Design Net Capacity | 1660 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2019 | 1660 | 3817 | 5356.14 | 100.00 | 100.00 | 100.00 | 92.30 | 92.30 |
2020 | 1660 | 8667 | 12454.80 | 98.70 | 96.80 | 97.60 | 85.40 | 87.10 |
2021 | 1660 | 7089 | 10870.50 | 80.90 | 77.70 | 89.10 | 74.80 | 81.80 |
2022 | 1660 | 5654 | 8297.85 | 64.50 | 57.10 | 79.50 | 57.10 | 74.40 |