Details

Reactor Type Pressurised Water Reactor (or PWR)
Model VVER V-392M
Owner Joint Stock Company 'Concern Rosenergoatom'
Operator Joint Stock Company 'Concern Rosenergoatom'

Timeline

Construction Start Sunday, 12 July 2009
First Criticality Friday, 22 March 2019
First Grid Connection Wednesday, 1 May 2019
Commercial Operation Thursday, 31 October 2019

Specifications

Capacity Net 1101 MWe
Capacity Gross 1181 MWe
Thermal Capacity 3200 MWt
Design Net Capacity 1114 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2019 1101 4222 3557.06 88.20 85.50 85.50 83.50 83.50
2020 1101 7367 7602.61 83.90 81.50 82.10 78.60 79.30
2021 1101 6953 7348.32 79.40 76.70 79.60 76.20 77.90
2022 1101 7368 7875.32 84.10 81.70 80.20 81.60 79.10

Source: Operating details - IAEA PRIS