Details

Reactor Type Pressurised Water Reactor (or PWR)
Model CPR-1000
Owner Fujian Ningde Nuclear Power Company, Ltd.
Operator Fujian Ningde Nuclear Power Company, Ltd.

Timeline

Construction Start Wednesday, 12 November 2008
First Criticality Friday, 20 December 2013
First Grid Connection Saturday, 4 January 2014
Commercial Operation Sunday, 4 May 2014

Specifications

Capacity Net 1018 MWe
Capacity Gross 1089 MWe
Thermal Capacity 2905 MWt
Design Net Capacity 1018 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2014 1018 7044 6568.05 100.00 99.80 99.80 97.60 97.60
2015 1018 7145 6528.23 81.60 80.60 88.30 73.20 83.00
2016 1018 6290 5714.85 71.60 86.20 87.50 63.90 75.80
2017 1018 8371 8252.86 95.60 98.70 90.60 92.50 80.40
2018 1018 7938 7953.87 90.60 89.00 90.20 89.20 82.30
2019 1018 8026 8079.09 91.60 90.60 90.30 90.60 83.70
2020 1018 8784 8940.50 100.00 100.00 91.80 100.00 86.20
2021 1018 7904 8043.49 90.20 90.20 91.60 90.20 86.70
2022 1018 8158 8303.72 93.10 93.10 91.70 93.10 87.40

Source: Operating details - IAEA PRIS