Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | CPR-1000 |
Owner | Fujian Ningde Nuclear Power Company, Ltd. |
Operator | Fujian Ningde Nuclear Power Company, Ltd. |
Timeline
Construction Start | Monday, 18 February 2008 |
---|---|
First Criticality | Saturday, 24 November 2012 |
First Grid Connection | Friday, 28 December 2012 |
Commercial Operation | Monday, 15 April 2013 |
Specifications
Capacity Net | 1018 MWe |
---|---|
Capacity Gross | 1089 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1018 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2012 | 1018 | 81 | 4.12 | - | - | - | - | - |
2013 | 1018 | 7369 | 6947.98 | 99.30 | 99.90 | 99.90 | 96.60 | 96.60 |
2014 | 1018 | 5119 | 5047.23 | 58.40 | 56.70 | 75.30 | 56.60 | 73.80 |
2015 | 1018 | 7798 | 7583.95 | 89.00 | 88.00 | 79.90 | 85.00 | 77.90 |
2016 | 1018 | 7207 | 6764.98 | 82.00 | 97.30 | 84.60 | 75.60 | 77.30 |
2017 | 1018 | 7177 | 7210.58 | 81.90 | 83.80 | 84.40 | 80.90 | 78.00 |
2018 | 1018 | 7756 | 8116.45 | 88.50 | 88.50 | 85.10 | 91.00 | 80.30 |
2019 | 1018 | 8567 | 8608.23 | 97.80 | 96.50 | 86.80 | 96.50 | 82.70 |
2020 | 1018 | 8007 | 8119.41 | 91.20 | 90.80 | 87.30 | 90.80 | 83.70 |
2021 | 1018 | 8070 | 8209.23 | 92.10 | 92.10 | 87.90 | 92.10 | 84.70 |
2022 | 1018 | 8760 | 8917.03 | 100.00 | 100.00 | 89.10 | 100.00 | 86.30 |