Details

Reactor Type Pressurised Water Reactor (or PWR)
Model VVER V-491
Owner Joint Stock Company 'Concern Rosenergoatom'
Operator Joint Stock Company 'Concern Rosenergoatom'

Timeline

Construction Start Saturday, 25 October 2008
First Criticality Tuesday, 6 February 2018
First Grid Connection Friday, 9 March 2018
Commercial Operation Monday, 29 October 2018

Specifications

Capacity Net 1101 MWe
Capacity Gross 1188 MWe
Thermal Capacity 3200 MWt
Design Net Capacity 1066 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2018 1085 3078 2344.91 25.10 23.80 23.80 20.30 20.30
2019 1101 6666 7137.13 76.10 74.40 67.20 74.00 66.40
2020 1101 7037 7530.82 80.10 82.60 74.30 77.90 71.70
2021 1101 8324 8598.45 95.00 90.50 79.40 89.20 77.20
2022 1101 7241 7714.52 82.70 80.20 79.60 80.00 77.90

Source: Operating details - IAEA PRIS