Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | AP1000 |
Owner | China Power Investment Group |
Operator | Shandong Nuclear Power Company, Ltd. |
Timeline
Construction Start | Sunday, 20 June 2010 |
---|---|
First Criticality | Saturday, 29 September 2018 |
First Grid Connection | Saturday, 13 October 2018 |
Commercial Operation | Wednesday, 9 January 2019 |
Specifications
Capacity Net | 1170 MWe |
---|---|
Capacity Gross | 1250 MWe |
Thermal Capacity | 3415 MWt |
Design Net Capacity | 1126 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2018 | 1170 | 1099 | 800.72 | - | - | - | - | - |
2019 | 1170 | 8711 | 9935.22 | 99.40 | 97.40 | 97.40 | 96.90 | 96.90 |
2020 | 1170 | 7983 | 9066.38 | 90.90 | 89.30 | 93.40 | 88.20 | 92.60 |
2021 | 1170 | 8139 | 9286.00 | 92.90 | 92.50 | 93.10 | 90.60 | 91.90 |
2022 | 1170 | 8519 | 9773.92 | 97.20 | 98.00 | 94.30 | 95.40 | 92.80 |