Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | CPR-1000 |
Owner | Cnnc Fujian Fuqing Nuclear Power Co., Ltd |
Operator | CNNC Fujian Fuqing Nuclear Power Co Ltd |
Timeline
Construction Start | Wednesday, 17 June 2009 |
---|---|
First Criticality | Wednesday, 22 July 2015 |
First Grid Connection | Thursday, 6 August 2015 |
Commercial Operation | Friday, 16 October 2015 |
Specifications
Capacity Net | 1000 MWe |
---|---|
Capacity Gross | 1089 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1000 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2015 | 1000 | 3487 | 2017.22 | 100.00 | 100.00 | 100.00 | 87.80 | 87.80 |
2016 | 1000 | 6807 | 6070.84 | 77.50 | 81.50 | 84.10 | 69.10 | 71.80 |
2017 | 1000 | 7659 | 7416.83 | 87.40 | 86.60 | 85.20 | 84.70 | 77.70 |
2018 | 1000 | 7587 | 7255.87 | 86.60 | 84.80 | 85.10 | 82.80 | 79.30 |
2019 | 1000 | 8685 | 7893.35 | 99.10 | 98.90 | 88.40 | 90.10 | 81.90 |
2020 | 1000 | 8137 | 7726.34 | 92.60 | 91.50 | 89.00 | 88.00 | 83.10 |
2021 | 1000 | 7781 | 7482.49 | 88.80 | 87.70 | 88.80 | 85.40 | 83.50 |
2022 | 1000 | 8610 | 8194.52 | 98.30 | 99.00 | 90.20 | 93.50 | 84.90 |