Details

Reactor Type Pressurised Water Reactor (or PWR)
Model CPR-1000
Owner Guangxi Fangchenggang Nuclear Power Company, Ltd.
Operator Guangxi Fangchenggang Nuclear Power Company, Ltd.

Timeline

Construction Start Friday, 30 July 2010
First Criticality Tuesday, 13 October 2015
First Grid Connection Sunday, 25 October 2015
Commercial Operation Friday, 1 January 2016

Specifications

Capacity Net 1000 MWe
Capacity Gross 1086 MWe
Thermal Capacity 2905 MWt
Design Net Capacity 1000 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2015 1000 1034 660.80 - - - - -
2016 1000 7761 7141.83 88.40 100.00 100.00 81.30 81.30
2017 1000 5794 5212.98 66.10 76.70 88.30 59.50 70.40
2018 1000 7622 7425.87 87.00 90.00 88.90 84.80 75.20
2019 1000 8736 8540.31 99.70 99.60 91.60 97.50 80.80
2020 1000 8140 7919.20 92.70 91.40 91.50 90.20 82.60
2021 1000 8179 8168.79 93.40 92.90 91.80 93.20 84.40
2022 1000 8499 8414.60 97.00 99.20 92.80 96.10 86.10

Source: Operating details - IAEA PRIS


See Also

Nuclear Power in China

Related News

WNN articles on China
Subscribe to receive updates on news