Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | CNP-600 |
Owner | Hainan Nuclear Power Company |
Operator | Hainan Nuclear Power Company |
Timeline
Construction Start | Sunday, 25 April 2010 |
---|---|
First Criticality | Monday, 12 October 2015 |
First Grid Connection | Saturday, 7 November 2015 |
Commercial Operation | Friday, 25 December 2015 |
Specifications
Capacity Net | 601 MWe |
---|---|
Capacity Gross | 650 MWe |
Thermal Capacity | 1930 MWt |
Design Net Capacity | 601 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2015 | 610 | 1006 | 43.73 | - | - | - | - | - |
2016 | 601 | 8185 | 3617.23 | 93.20 | 94.00 | 94.00 | 68.50 | 68.50 |
2017 | 601 | 7006 | 3405.19 | 80.00 | 80.00 | 87.00 | 64.70 | 66.60 |
2018 | 601 | 7711 | 3909.29 | 88.00 | 87.50 | 87.20 | 74.20 | 69.20 |
2019 | 601 | 7741 | 4352.30 | 88.40 | 87.50 | 87.20 | 82.70 | 72.50 |
2020 | 601 | 7933 | 4519.05 | 90.30 | 91.50 | 88.10 | 85.90 | 75.20 |
2021 | 601 | 8044 | 4467.67 | 91.80 | 92.60 | 88.80 | 84.90 | 76.80 |
2022 | 601 | 8760 | 5195.39 | 100.00 | 99.90 | 90.40 | 98.70 | 79.90 |