Details

Reactor Type Fast Reactor (or FBR)
Model BN-800
Owner Joint Stock Company 'Concern Rosenergoatom'
Operator Joint Stock Company 'Concern Rosenergoatom'

Timeline

Construction Start Tuesday, 18 July 2006
First Criticality Friday, 27 June 2014
First Grid Connection Thursday, 10 December 2015
Commercial Operation Monday, 31 October 2016

Specifications

Capacity Net 820 MWe
Capacity Gross 885 MWe
Thermal Capacity 2100 MWt
Design Net Capacity 820 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2015 820 23 34.55 - - - - -
2016 820 5453 3456.96 96.40 81.90 81.90 82.00 82.00
2017 820 6551 5165.75 74.80 71.80 73.30 71.90 73.40
2018 820 5680 4408.98 64.80 61.20 67.70 61.40 67.80
2019 820 6196 4909.25 70.70 68.30 67.90 68.30 68.00
2020 820 7373 5934.14 83.90 81.90 71.30 82.40 71.40
2021 820 4049 3087.27 46.20 43.30 65.90 43.00 65.90
2022 820 6710 5174.47 76.60 71.60 66.80 72.00 66.90

Source: Operating details - IAEA PRIS