Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | APR-1400 |
Owner | Emirates Nuclear Energy Corporation |
Operator | Nawah Energy Company |
Timeline
Construction Start | Monday, 15 April 2013 |
---|---|
First Criticality | Friday, 27 August 2021 |
First Grid Connection | Tuesday, 14 September 2021 |
Commercial Operation | Thursday, 24 March 2022 |
Specifications
Capacity Net | 1337 MWe |
---|---|
Capacity Gross | 1417 MWe |
Thermal Capacity | 3983 MWt |
Design Net Capacity | 1310 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2021 | 1345 | 1891 | 1200.19 | - | - | - | - | - |
2022 | 1337 | 7723 | 9914.13 | - | - | - | - | - |