Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | APR-1400 |
Owner | Emirates Nuclear Energy Corporation |
Operator | Nawah Energy Company |
Timeline
Construction Start | Wednesday, 24 September 2014 |
---|---|
First Criticality | Thursday, 22 September 2022 |
First Grid Connection | Saturday, 8 October 2022 |
Commercial Operation | Friday, 24 February 2023 |
Specifications
Capacity Net | 1337 MWe |
---|---|
Capacity Gross | 1417 MWe |
Thermal Capacity | 3983 MWt |
Design Net Capacity | 1310 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2022 | 1337 | 1703 | 1189.53 | - | - | - | - | - |